The Mikado Method — Optimize¶
Source: Ola Ellnestam & Daniel Brolund, The Mikado Method (Manning, 2014)
Each "before" is a refactoring situation about to be tackled badly. Produce the Mikado graph and plan — or argue that a simpler approach beats Mikado here. The skill being trained: choosing the right strategy, then sequencing it leaf-first.
Situation 1 — Remove a god-object reference¶
Before. AppContext is a static god-object (AppContext.get().db(), .cache(), .userSession(), .featureFlags()). CheckoutController calls all four. You want CheckoutController to receive what it needs explicitly.
Plan. Mikado fits — deep, unknown fan-out. Goal: "CheckoutController receives Db, Cache, UserSession, FeatureFlags via constructor; no AppContext.get() in the class." First attempt reveals four prerequisites (one per accessor) plus caller breaks:
[~] GOAL: CheckoutController takes Db, Cache, UserSession, FeatureFlags via ctor
├── [ ] read db from injected field (overloaded ctor, default AppContext.get().db())
├── [ ] read cache from injected field (overloaded ctor default)
├── [ ] read session from injected field (overloaded ctor default)
├── [ ] read flags from injected field (overloaded ctor default)
└── [ ] caller(s) of new CheckoutController() pass the four collaborators
Each accessor leaf is independent (Parallel Change: overloaded ctor defaulting to the AppContext value, switch body to field, commit). Caller leaf last, then root removes the defaults. Optimization insight: if AppContext.get() appears under every controller's graph, the real finding is "AppContext is a pervasive coupling point" — schedule its removal as its own initiative rather than fighting it controller-by-controller forever.
Situation 2 — A two-line rename dressed up as a migration¶
Before. Someone proposes a Mikado graph to rename calcTotal() → calculateTotal() across 40 call sites and "carefully migrate."
Argue simpler. Don't use Mikado. Scope is fully known and the change is mechanical — the IDE's Rename refactoring updates all 40 sites atomically and safely in one green step. There's no unknown dependency tree to discover, so there are no leaves to find. A graph here is pure overhead. Reserve Mikado for deep, unknown-dependency changes.
Situation 3 — Untangle vs. strangle¶
Before. LegacyPricing (1,800 lines, no tests, reaches into 6 globals, called from 22 places) must be replaced by a new pricing engine. The team's instinct: in-place Mikado.
Plan / argue. First do a learning spike to draw the graph (the build is slow and the class is huge, so a tight revert loop is painful — junior.md §9). If the spike's graph is wide-but-shallow and the globals are few real seams, in-place Mikado works: extract a PricingEngine interface (Branch by Abstraction) as the first shared leaf, migrate callers to it, then swap the implementation.
But if the graph comes back dense and cyclic — globals tangled across all 22 callers, cycles you'd have to break everywhere — argue for a Strangler at code level instead: stand the new engine up behind the same interface, route callers over one at a time, and delete LegacyPricing when traffic is zero. The Mikado graph is exactly the evidence that justifies the strangle: "untangling in place is N leaves of cyclic risk; strangling is M independent caller-cutovers." Also: get characterization tests on LegacyPricing first either way — without a green signal, neither approach is safe.
Situation 4 — The deep, narrow chain¶
Before. Proposed graph:
[~] GOAL: A uses new format
└── [ ] B must change
└── [ ] C must change
└── [ ] D must change
└── [ ] E must change
Optimize. A deep, single-child chain is a smell: zero parallelism, no early shippable value, and a long sequential risk. Before executing, ask whether the goal can be re-cut so more work is independent — e.g. introduce an abstraction at B so that C/D/E migrate behind it independently rather than in lockstep. If the chain is genuinely irreducible (a true linear pipeline), Mikado still works, but you commit E→D→C→B→A bottom-up and accept that there's nothing to parallelize. Set stakeholder expectations accordingly: this one is a relay, not a swarm.
Situation 5 — Behavior change smuggled into a refactor¶
Before. "While I'm Mikado-ing OrderService onto constructor injection, I'll also fix the rounding bug and add the new loyalty discount."
Optimize / argue. Separate the concerns — Mikado is for structure only. Mikado's signal is "green build = behavior preserved." If you also change behavior, a green build no longer means "I didn't break anything," and the revert discipline loses its meaning (you can't tell a behavior regression from intended change). Plan: (1) run the structural Mikado refactor to constructor injection, committing green leaves; (2) then, on a clean green baseline with the class now testable, fix the rounding bug and add the discount as ordinary TDD changes. Mixing them forfeits the method's core guarantee.
Situation 6 — Parallelize a wide graph¶
Before. A real graph after the discovery phase, three engineers free:
[~] GOAL: ReportingService takes ReportRepository (no static DB)
├── [~] A: PdfRenderer subtree (3 leaves)
├── [~] B: CsvRenderer subtree (2 leaves)
├── [~] C: Scheduler subtree (2 leaves)
└── [ ] X: extract ReportRepository interface <-- needed by A, B, and C
Plan. Optimize for throughput without creating merge contention. X is a shared serialization barrier — one engineer does it first, everyone rebases on the green commit. Then fan out: engineer 1 owns subtree A, engineer 2 owns B, engineer 3 owns C — whole subtrees, not interleaved leaves, so no shared files. Every cleared leaf commits green to trunk for continuous integration. Only the GOAL (root) waits for all three subtrees; assign it to whoever finishes last. Anti-pattern avoided: handing out individual leaves across subtrees would create overlapping edits and merge conflicts — and starting the fan-out before X is done would force everyone to re-do the interface extraction.
Situation 7 — Estimate from a partial graph¶
Before. Two days into a refactor, stakeholders want a date. You have 9 leaves committed; the last three attempts added 5, 3, and 2 new prerequisites respectively; the graph currently shows 7 open leaves; average leaf cost ≈ 1.5 hours.
Optimize the answer. Don't give a point estimate. Compute: lower bound = 7 open × 1.5h ≈ 10.5h of known work. Trend = discovery rate is falling (5 → 3 → 2 new per attempt), so the graph is converging — open count should keep shrinking. Report a range with the trend: "we've cleared 9 leaves; ~7 known remain (≈1.5 days), and the rate of new discoveries is dropping fast, so I expect it to land within 2–3 days, all shipped green as we go — and we can stop at any leaf with banked, shippable value." That is a defensible, decision-useful estimate; "Thursday" is not.